Baselines

Project Baselines (Baseline / Baseline1–10)

Baseline / Baseline1–10 Start/Finish/Duration/Work vs P6 targets

Microsoft Project Set Baseline dialog. Set baseline to Baseline, Entire project. Set interim plan is a different option.
Project → Set Baseline. A baseline is a stored snapshot, not Current Date.

What Microsoft stores

A baseline is a snapshot of scheduled values. Microsoft: nearly 20 reference points in five categories — start, finish, duration, work, cost. You can save 11 baselines per project: the unnumbered Baseline plus Baseline 1 through Baseline 10.

When you set a baseline, Project copies the currently scheduled fields into the matching baseline fields.

FieldMicrosoft meaning
Baseline Startplanned beginning at save time (copy of Start). "NA" until set
Baseline Finishplanned completion at save time (copy of Finish). "NA" until set
Baseline Durationoriginal span (copy of scheduled duration). "0 days" until set
Baseline Worktotal planned person-hours (copy of Work). "0 hours" until set

Variance fields (Start/Finish/Work Variance, etc.) use the unnumbered Baseline, not Baseline1–10, unless you build a custom comparison.

MSPDI: repeating Task/Baseline (also on Resource and Assignment). Required child Number = "unique number of the baseline data record." Start / Finish / Duration / Work / Cost are optional children. Timephased baseline data is optional. Unverified: whether Number 0 is the unnumbered Baseline and 1–10 are Baseline1–10 — that is the natural reading, not an Oracle/Microsoft sentence we fetched.

Interim plans are not baselines: they save only current start and finish (up to 10). Do not map them to P6 baselines.

Contrast with P6

P6Project
SnapshotSeparate baseline project (copy of the project)Fields on the same task (Baseline0–10)
How many in useMany exist; four assigned at once (Project + 3 user)11 field sets on the task
Activity planned datesTASK.target_start_date / target_end_date (Planned — not baseline)Start / Finish (current), Baseline* (snapshot)
In XERProfessional table: XER does not carry baselinesMSPDI Baseline elements can
In P6 XMLXML does carry baselinesn/a

Do not map P6 planned/target dates to Project Baseline Start/Finish. Planned dates keep moving until the activity starts (Oracle). Baseline fields stay put until you set/clear them (Microsoft).

See p6/baselines.md. Never write a real MPP to hold baselines; generate MSPDI (convert/mpxj.md).