Project Task Types: Fixed Units, Fixed Duration, Fixed Work

Fixed Units, Fixed Duration, Fixed Work + MSPDI integers

Microsoft Project Information dialog. Start date is a different field from Status date.
This is Project Information. Task type is Fixed Units, Fixed Duration, or Fixed Work, not this dialog.

Formula (Microsoft): Work = Duration × Units.

Fixing one value tells Project not to change it when the other two change.

Task typeIf you revise unitsIf you revise durationIf you revise work
Fixed Units (default)Duration recalculatedWork recalculatedDuration recalculated
Fixed WorkDuration recalculatedUnits recalculatedDuration recalculated
Fixed DurationWork recalculatedWork recalculatedUnits recalculated
  • Fixed Units: people (units) stay put. Default. File > Options > Schedule sets the default for new tasks.
  • Fixed Work: work stays put. Always effort-driven; you cannot turn effort-driven off.
  • Fixed Duration: duration stays put (meetings, curing time).

MSPDI integers

Microsoft Learn, Task Type element:

ValueMeaning
0Fixed units
1Fixed duration
2Fixed work

Interaction with effort-driven

Effort-driven is a separate yes/no except on Fixed Work (always on). See effort-driven.md. Adding a resource to a Fixed Units + effort-driven task shortens duration; adding a resource to a Fixed Duration + effort-driven task reduces work per resource.

P6 duration_type is a different enum (Fixed Units, Fixed Duration & Units, Fixed Units/Time, etc.). Do not assume the integers match. Mapping is conversion work, not identity.