Codes, UDFs & Notes

Notebooks (MEMOTYPE / TASKMEMO / WBSMEMO) — Not Schedule Logic

Notebooks are text on a topic; not steps, UDFs, or schedule logic

P6 General tab. WBS, Responsible Manager, and Primary Resource sit as fields.
These are General-tab fields. A notebook is a memo topic, not a schedule field.

What a planner means

A notebook is text on a topic (scope, change, safety, “why this lag”). It does not date the activity, hold a relationship, or change float.

XER tables (Oracle)

MEMOTYPE — the topic dictionary:

ColumnOracle label
memo_type_idUnique ID
memo_typeNotebook Topic
seq_numSort Order
eps_flagAvailable for EPS
proj_flagAvailable for Projects
wbs_flagAvailable for WBS
task_flagAvailable for Activity

TASKMEMO — activity notebook body: memo_id, memo_type_id, task_id, proj_id, task_memo (Notebook Description).

WBSMEMO — EPS / project / WBS notebook: wbs_memo_id, memo_type_id, wbs_id, proj_id, wbs_memo.

One activity can have several TASKMEMO rows (one per topic). The topic flags say where that topic is allowed, not that a row exists.

What it is not

  • Not an activity step (TASKPROC).
  • Not a UDF (UDFVALUE).
  • Not the activity name or notebook-as-WBS.
  • Not a constraint or Expected Finish.

Microsoft Project

Project has a single Notes field on the task (and resource/assignment notes). No topic dictionary, no EPS/WBS/activity flags.

Do not explode TASKMEMO into subtasks or WBS bands, or concatenate every topic into Activity Name. A Viewer can show notebooks as text. A converter may map one topic into MSP Notes; that is a product choice, not an identity. Do not invent an MSPDI NotebookTopic table.