Resources & Cost

Units of Measure Label Material, Not Labor Time

UMEASURE labels material; labor/nonlabor units are time

P6 Resources tab. Assignment columns include units.
These are assignment units. Units of measure are an Admin dictionary, not this tab.

What a planner means

A unit of measure is the label on a material resource (tons, m³, EA, box). Oracle API: labor and nonlabor units are time. Material units come from the UnitOfMeasure dictionary.

Professional: a unit of measure “describes the quantity of a particular resource.” Labor is hours or days; materials can be cubic/linear feet, tons, kilos; each-items can be EA, box, case, pallet. Money is a currency, not this dictionary.

EPPM: create Unit Abbreviation + Unit Name under Enterprise Data / Resources / Units of Measure, then assign the unit to a material resource (RSRC.unit_id).

Help also says you can change units in a project to change how graphs and spreadsheets depict materials, and that abbreviations are used for conversions. Do not invent a conversion table; Oracle does not publish the formula on the cited pages.

PROJCOST.qty_name is labeled Unit of Measure on an expense. That is a string on the expense row, not UMEASURE.unit_id.

XER

UMEASURE (Units of Measure):

ColumnOracle label
unit_idUnique ID
unit_nameUnit Name
unit_abbrevUnit Abbreviation
seq_numSort Order

RSRC.unit_id is Unit of Measure. No TASK unit-of-measure column on the project map.

Microsoft Project

MSP material resources have a Material Label (yards, tons). That is a string on the resource, not a shared UMEASURE dictionary. Do not map unit_id to Work or to Duration.

Don't

  • Treat UMEASURE as labor/nonlabor time or as a currency.
  • Put unit_id on TASK.
  • Treat PROJCOST.qty_name as UMEASURE.unit_id.
  • Invent abbreviation conversion math.
  • Map UMEASURE to MSP Work.