P6 Resources tab on an activity. Column headers include Resource, Units / Time, Start, Finish, Budgeted Units, Role. Add Resource, Add Role, Assign by Role sit on the tab.

Collection

Resources & Cost

People, cost, leveling · 24 topics.

Resources are assignments on the activity (Add Resource / Add Role), not a WBS row.

Topics

24

  1. A Role

    A role is a skill; not RSRC; not MSP Generic; staff later

    Resources & Cost
  2. A Shift

    Shift is 24h limits for leveling; not a calendar; EPPM leveler ignores it

    Resources & Cost
  3. Assignment Codes Tag TASKRSRC, Not the Resource

    Assignment codes tag TASKRSRC; not the resource or the role

    Resources & Cost
  4. Assignment Lag

    Assignment lag ≠ relationship lag; Drive Activity Dates is a flag

    Resources & Cost
  5. Cost Accounts Are a Chart of Accounts, Not a Price

    ACCOUNT hierarchy on assignments/expenses; not a price; not MSP rate tables

    Resources & Cost
  6. Expense Categories Label Expenses, Not Cost Accounts

    COSTTYPE labels expenses; not ACCOUNT; no parent

    Resources & Cost
  7. Expenses and Accrual (PROJCOST) — Not Resource Units

    PROJCOST expenses + accrual; not resource units; not a resource curve

    Resources & Cost
  8. Funding

    Funding source is who pays; not Original Budget, not spending plan

    Resources & Cost
  9. Group and Sort Resource Usage Spreadsheet Columns in the Resource Assignments Window Is Display Options Bar, Group and Sort By

    Group and sort Resource Usage Spreadsheet columns in the Resource Assignments window is Display Options bar, Group and Sort By

    Resources & Cost
  10. Overhead Codes Are Non-Project Timesheet Time

    Overhead is non-project timesheet time; not on project XER

    Resources & Cost
  11. Primary Resource

    Primary resource is RSRC; owner is a user (TASKUSER); not the same

    Resources & Cost
  12. Rate Types Are Five Named Price/Unit Slots

    Five named Price/Unit slots; Rate Source is Resource/Role/Override

    Resources & Cost
  13. Recalculate Assignment Costs Rewrites Costs from Current Rates

    Recalculate Assignment Costs rewrites assignment costs from current rates; not Calculate schedule; Override skipped

    Resources & Cost
  14. Resource and Role Teams Are View Groups, Not Resources

    Resource/role teams group members for views; not on project XER

    Resources & Cost
  15. Resource Codes Tag Resources, Not Activities

    Resource codes tag resources; global; not activity or project codes

    Resources & Cost
  16. Resource Curves (Not MSP Work Contours)

    21-point curves on Fixed Duration assignments; not MSP work contours

    Resources & Cost
  17. Resource Leveling Delays Work Until Units Fit

    Leveler delays activities to fit max units; not Calculate schedule; no Leveling Delay column

    Resources & Cost
  18. Resource Usage Profile

    Resource Usage Profile is a Show-on-Bottom histogram of resource/role units/cost; stacked histogram, limits, overallocation; not the usage spreadsheets or…

    Resources & Cost
  19. Resource Usage Spreadsheet

    Resource Usage Spreadsheet is a timescaled resource/role view; buckets typed here; Open Projects Only / gray cells / Excel paste; no XER table

    Resources & Cost
  20. Role Codes Tag Roles, Not Resources

    Role codes tag roles; not resource codes; not assignment codes

    Resources & Cost
  21. RSRC / TASKRSRC (and Roles / Prices)

    RSRC / TASKRSRC units, price, role vs resource

    Resources & Cost
  22. Spending Plan

    Monthly spend/benefit on WBS; Current Budget is orig + approved log

    Resources & Cost
  23. Timesheets Are Approved Hours; Apply Actuals Posts Them

    Approved Team Member hours; Apply Actuals posts; periods ≠ FINDATES

    Resources & Cost
  24. Units of Measure Label Material, Not Labor Time

    UMEASURE labels material; labor/nonlabor units are time

    Resources & Cost