Remaining Duration vs Remaining Finish (Not the Same Object)

Remaining duration is hours; Remaining Finish is a date

P6 Status tab. Duration Original / Actual / Remaining / At Complete. Started and Finished date fields. Physical %. Total Float and Free Float.
Actual Start/Finish are dates. Remaining duration is hours. Physical % is a different field.

Remaining duration

A length of working time. Oracle: total working time from remaining start to remaining finish, using the activity calendar. Before start = planned duration. After finish = 0. XER: TASK.remain_drtn_hr_cnt (hours). See P6 Remaining Duration vs Percent Complete.

Remaining Finish (Remaining Early Finish)

A date. Oracle Professional: “The earliest possible date the remaining work for the activity is scheduled to finish.” Calculated by the scheduler; can be typed; overwritten when you schedule. Before start = Planned Finish. After finish = blank.

XER: TASK.reend_date (Remaining Early Finish). Remaining Early Start is restart_date.

Unifier/EVM (same product family): Remaining Early Finish is calculated by adding remaining duration to remaining early start. After complete, both remaining dates blank.

Professional also: once started, Remaining Start = Data Date (unless you are in a leveling/preserve-early-dates case). Early Finish equals Remaining Finish unless you preserve scheduled early dates during leveling.

Related, not equal

Remaining durationRemaining Finish
KindHours of calendar workA clock date
Blank when complete0 hoursblank date
Typing itChanges Duration % Complete pairScheduler will overwrite on the next Calculate schedule
CalendarDuration is measured on the activity calendarDate is placed by walking that duration from remaining start

Expected Finish is a third object (typed forecast). Must Finish By is a project constraint. Neither is Remaining Finish.

Microsoft Project

Finish / Remaining Finish in Project is the scheduled finish. Remaining Duration is Duration − Actual Duration. Do not treat P6 Remaining Finish as remaining duration, or write a remaining-finish date into MSPDI Duration. Walking remaining hours across the activity calendar is how you get the date — do not add 8h × N calendar days.