P6 Status tab. Duration Original, Actual, Remaining, and At Complete sit beside Started and Finished date fields, Physical %, Total Float, and Free Float.

Collection

Dates & Status

As-of dates, actuals, remaining work · 12 topics.

Actual Start/Finish are dates. Remaining duration is hours. They are not the same field.

Topics

12

  1. Actual Start/Finish Are Dates; Remaining Duration

    Actual Start/Finish are dates; remaining duration is hours; not MSP Duration−Actual

    Dates & Status
  2. Anticipated Start/Finish Are WBS Planning Dates, Not Activity Dates

    Anticipated Start/Finish are WBS planning dates; not on TASK; Calculate schedule does not move them

    Dates & Status
  3. Apply Actuals Posts Progress and Moves the Data Date

    Apply Actuals posts plan or timesheets and moves Data Date; not Store Period

    Dates & Status
  4. Expected Finish (Not Remaining Finish, Not a Constraint)

    Expected Finish is a typed forecast; scheduler honors it only if the option is on

    Dates & Status
  5. External Early Start / Late Finish Stand in for a Missing Project

    External Early Start / Late Finish stand in for a lost interproject link

    Dates & Status
  6. Must Finish by (Project Constraint, Not Data Date)

    Must Finish By is a project-end constraint; not Data Date; sets the backward pass

    Dates & Status
  7. P6 Data Date (Time-Now / As-Of)

    Data Date (as-of); XER last_recalc_date vs Must Finish By; live 31-Jul-26 17:00

    Dates & Status
  8. P6 Remaining Duration vs Percent Complete

    Remaining duration vs Duration / Physical / Units % Complete

    Dates & Status
  9. Remaining Duration vs Remaining Finish (Not the Same Object)

    Remaining duration is hours; Remaining Finish is a date

    Dates & Status
  10. Status Date vs P6 Data Date (Microsoft Project)

    Status Date vs P6 Data Date; what it drives

    Dates & Status
  11. Suspend / Resume (Not a Calendar Exception, Not an MSP Split)

    Suspend/Resume is activity nonwork; not a calendar exception; not an MSP split

    Dates & Status
  12. Update Progress Estimates On-Schedule Progress for a New Data Date

    Update Progress estimates on-schedule progress for spotlighted or selected activities; not Apply Actuals, not Spotlight

    Dates & Status
Back to top