Dates & Status

Anticipated Start/Finish Are WBS Planning Dates, Not Activity Dates

Anticipated Start/Finish are WBS planning dates; not on TASK; Calculate schedule does not move them

P6 Activities grouped by WBS. Green WBS bands sit above activity rows.
These are activity rows under WBS bands. Anticipated dates live on the WBS, not on TASK.

What a planner means

Anticipated Start and Anticipated Finish are typed dates on a project, EPS node, or WBS during planning. Oracle: manually entered; not affected by scheduling. Cannot be entered on an activity.

Oracle: if the WBS (or project) has no activities, Anticipated Start/Finish are used as that row’s Start/Finish. If there are no children, the anticipated date is the start/finish listed for the item.

Once activities exist, Calculate schedule rolls up from TASK dates. Anticipated is then a planning leftover, not the bar.

This is not Expected Finish (activity; primary resource; optional scheduler input). See Expected Finish (Not Remaining Finish, Not a Constraint). Not Planned Start (TASK.target_start_date). Not External Early Start. Not Must Finish By.

The project itself is a PROJWBS row (proj_node_flag). Project anticipated dates live there. See P6 WBS and EPS.

XER

ColumnOracle label
PROJWBS.anticip_start_dateAnticipated Start
PROJWBS.anticip_end_dateAnticipated Finish

No TASK columns. Do not invent TASK.anticip_start_date.

Microsoft Project

Desktop Project has no Anticipated Start on a summary. A typed Start on a summary is either a rollup or a constraint, and Calculate schedule can move it. Manual-mode placeholder text is not the same object. Do not map Anticipated to Baseline Start or to SNET.

Don't

  • Treat Anticipated Start/Finish as activity dates, as calculated dates, or as the Gantt bar when activities exist.
  • Store them on TASK.
  • Map them to Expected Finish, Planned Start, External Early Start, Must Finish By, or MSP Baseline.

Sources

Back to top