In Primavera P6

Add a Bar to the Gantt Chart

Add a bar to the Gantt Chart is View, Bars; Add; Display; name; Timescale; Filter; Apply

P6 Gantt of sample EC00515. Horizontal bars on a quarter/month timescale with relationship arrows.
These bars come from the layout Bars list. Add a bar is View, Bars then Add, not dragging a new activity.

What a planner means

Add a bar to the Gantt Chart is Oracle Add a bar to the Gantt Chart. View, Bars; or Layout Options bar → Bars. Add. Mark Display. Type a name. Choose Timescale and Filter. Configure Bar Style, Bar Settings, and Bar Labels. Apply previews. Default restores the default bar settings. It is a how-to. It is not stored as its own table. It does not create, edit, or delete a relationship. It is not the Gantt bars object note, not Change a bar in the Gantt Chart, not Delete a bar from the Gantt Chart, not Position a bar in the Gantt Chart, not Display the Gantt Chart, not Move around a Gantt Chart, not Change an activity's start and finish dates in the Gantt Chart, not Change an activity's duration in the Gantt Chart, not View activity relationships in the Gantt Chart, not Create / Edit / Delete relationships in the Gantt Chart, not Progress Line, not a curtain, not TASKPRED, not EPPM Configuring Activity View Gantt Chart Bars / About Bars copied onto Professional, and not Microsoft Format Bar.

Oracle does print a how-to titled Add a bar to the Gantt Chart. Oracle does not print a menu item named Add a bar to the Gantt Chart. The menu that how-to prints is View, Bars. Do not invent View > Add a bar.

Oracle Add a bar to the Gantt Chart (Professional):

  • "To preview your changes, click Apply."
  • "To restore the default bar settings, click Default."
  • "Choose View, Bars. You can also click the Layout Options bar and choose Bars."
  • "Click Add."
  • "Mark the Display checkbox next to the new bar."
  • "Type a name for the new bar."
  • "In the Timescale column, select the timescale you want the new Gantt Chart bar to represent."
  • "In the Filter column, choose the filter you want to attach to the bar. Filters determine which activities the bar represents."
  • "Click the Bar Style tab and configure the new bar's style. The Preview column shows you what the configured bar will look like in the Gantt Chart."
  • "Click the Bar Settings tab and select grouping and necking options."
  • "Click the Bar Labels tab and specify the new bar's label and position."

That how-to fetched prints no OK, no Save, no Yes, no Bar Type list, no Add menu, and no Click Gantt View. Do not invent those on this how-to.

Gantt bars is a different object note. The Bars dialog as layout settings. This how-to is Add. See Gantt Bars Are Layout Bar Definitions, Not an XER Table.

Display the Gantt Chart is a different how-to. It opens the view. See Display the Gantt Chart.

Professional vs EPPM

Professional — View, Bars / Layout Options bar → Bars; Add; Display; name; Timescale; Filter; Bar Style / Bar Settings / Bar Labels; Apply; Default. No Save on that page.

EPPM web — Oracle Configuring Activity View Gantt Chart Bars: "Click the Add menu and select Bar or Label to add a new bar or label." Bar Type, Height, Bar Color, User Defined Start Date Field / Finish Date Field; Apply. That page fetched does not print View, Bars, Display checkbox, Timescale column, Filter column, Bar Settings, or Default. Do not copy Professional View, Bars / Filter column onto EPPM. Do not copy EPPM Add menu / Bar Type / Apply-only onto Professional as if they were the same how-to.

Primavera Cloud is a different product. Do not copy it here.

XER

The how-to is not an XER table. Oracle’s project XER map TOC has no GANTTBAR / ADDBAR / BARSTYLE / LAYOUTBAR table. Do not invent a view %T. Adding a bar definition does not write TASK. Layouts travel as .plf. A Viewer cannot reconstruct that the planner used this how-to.

Microsoft Project

Microsoft Project can format or add Gantt bar styles. Do not map that as P6 Add a bar to the Gantt Chart. Do not claim MPXJ writes a real MPP.

Don't

  • Invent View > Add a bar, or invent OK / Save / Bar Type on this how-to.
  • Collapse this onto the Gantt bars object note, Change a bar, or Delete a bar.
  • Copy EPPM Add menu / Bar Type onto Professional, or Professional Filter column / Default onto EPPM.
  • Invent a GANTTBAR XER table, or reconstruct the how-to from TASK dates.
  • Map MSP Format Bar as this how-to.
  • Claim MPXJ writes a real MPP.