In Primavera P6

View a Profile of Resource Allocation Across All Projects

View a profile of resource allocation across all projects is Show All Projects

P6 Resources tab. Assignment columns and Add Resource / Add Role.
This assignment is on one activity. View Resource Usage Profile allocation for all projects is enterprise, not this tab.

What a planner means

View a profile of resource allocation across all projects is Oracle View a profile of resource allocation across all projects. Activities window; View, Show on Bottom, Resource Usage Profile (or Layout Options bar → Show on Bottom, Resource Usage Profile). In the right pane, Display Options bar → Show All Projects (a check next to Show All Projects means it is selected). Left pane Display Options bar → Select View, By Resource or By Role. It is a how-to. It is not stored as its own table. It does not create, edit, or delete a relationship. It is not the Resource Usage Profile object note, not Display the Resource Usage Profile (open only), not View a profile of resource allocation for a specific project, not Define the Resource Usage Profile, not TASKPRED, not EPPM copied onto Professional, and not Microsoft Resource Graph options.

Oracle does print a how-to titled View a profile of resource allocation across all projects. Oracle does not print a menu item named View a profile of resource allocation across all projects. The path that how-to prints is Show on Bottom, then Show All Projects. Do not invent View > View a profile of resource allocation across all projects.

Oracle View a profile of resource allocation across all projects (Professional):

  • "In the Activities window, choose View, Show on Bottom, Resource Usage Profile."
  • "You can also click the Layout Options bar, then choose Show on Bottom, Resource Usage Profile."
  • "In the right pane of the bottom layout window, click the Display Options bar and choose Show All Projects, if it is not already selected. A check next to Show All Projects indicates that it is selected."
  • "To view total allocation by resource, click the Display Options bar in the left pane of the bottom layout window, then choose Select View, By Resource."
  • "To view total allocation by role, click the Display Options bar in the left pane of the bottom layout window, then choose Select View, By Role."
  • Tip: "When viewing total resource allocation across all projects, you can include resource limits, planning limits, overallocation, and available units in the profile. You can specify whether you want to display remaining units as one value or as separate values for open versus closed projects. When viewing by role, an additional option is available for displaying remaining units as separate values for staffed versus unstaffed projects."
  • Tip: "When viewing past period actual values across all projects, the profile displays summary past period actual values for closed projects."
  • Note: "Bars do not display for summary rows if your selection contains a mixture of labor/ nonlabor and material resources. Dashes display in the Total and Cumulative columns in the profile details."
  • Note: "Bars and cumulative curves with negative values do not display in the profile. You can view the negative values in the profile details. Double-click in the profile to view the profile details."

That how-to fetched prints no OK, no Apply, no Save, no Yes, and no Resource Usage Profile Options dialog. Do not invent those on this how-to. How to turn on limits / overallocation / available units is Regular Histogram define, not this page.

The Resource Usage Profile is a different object note. Leave Resource Usage Profile as the object.

Display the Resource Usage Profile is a different how-to. Show on Bottom only. See Display the Resource Usage Profile.

View a profile of resource allocation for a specific project is a different how-to. Do not collapse it onto Show All Projects.

Professional vs EPPM

Professional — View, Show on Bottom, Resource Usage Profile; right pane Display Options bar → Show All Projects; left pane By Resource or By Role. No OK / Apply on this how-to page.

EPPM web — the Professional how-to page is the source for this note. Do not invent an EPPM Show All Projects control. Do not copy Professional Display Options bar onto EPPM.

Primavera Cloud is a different product. Do not copy it here.

XER

The how-to is not an XER table. Oracle’s project XER map TOC has no RSRUSAGE / SHOWALLPROJECTS table. Do not invent a view %T. Show All Projects does not write TASK. Layouts travel as .plf. A Viewer cannot reconstruct that the planner used this how-to.

Microsoft Project

Microsoft Project can show a Resource Graph. Do not map that as P6 View a profile of resource allocation across all projects. Do not claim MPXJ writes a real MPP.

Don't

  • Invent View > View a profile of resource allocation across all projects, OK, Apply, Save, or Yes.
  • Collapse this onto Display the Resource Usage Profile, the specific-project how-to, Regular/Stacked define, or the Resource Usage Profile object.
  • Invent how to mark Show Limit / Overallocation on this page (the tip only says you can include them).
  • Copy Professional Show All Projects onto EPPM.
  • Invent a SHOWALLPROJECTS XER table, or reconstruct the how-to from TASKRSRC.
  • Map MSP Resource Graph as this how-to.
  • Claim MPXJ writes a real MPP.